Your browser does not support JavaScript!
Eurosystem Key Features

Eurosystem Aluminium Lightweight Crane System Key Features:

  • 1. Locking plates They can be dismantled, act us a buffer, dust protection and they complete the installation.
  • 2. Sizes of Beam 4 profile sizes available.
  • 3. Rail Connections A perfect cut, pin pointer, 16 point locking system which is easy to implement: one of the features that make the difference.
  • 4. Suspensions There are several suspension types are available depending on the type of beam used and the type of host structure.
  • 5. Hoisting Options Choose from Manual Chain Hoists, Electric Chain Hoists and Electric Wire Rope Hoists

OVERHEAD CRANE SYSTEM FOR THE SCENE DOCK AT THE NATIONAL THEATRE'S 'DORFMAN THEATRE'

The National Theatre required an overhead crane system to be installed on the scene dock for the Dorfman Theatre to assist their teams with set builds.

The crane system the NT required would need to maximise their operational space and to achieve this a low headroom solution would be the best choice. The work space’s ceiling where the crane is to be installed was not entirely level, so our engineers would need to plan and agree a suitable suspension method for the crane.

READ MORE
Overhead Crane System for the scene dock at the National Theatres Dorfman Theatre
Overhead Crane System, Industrial

BESPOKE OVERHEAD CRANE SYSTEM, MANUFACTURING PLANT

This busy manufacturing plant needed a bespoke crane system to be designed, manufactured and installed with minimal disruption to their operation.

Works had recently been completed at the plant and due to the tight production schedule there was no scope to move machinery, ducting or conveyor equipment. Our installations team had to plan working around the existing machinery and would also need to complete installation had to be completed and satisfactorily tested during a very brief shutdown and maintenance window.

READ MORE

PARTICLE ACCELERATION EXPERIMENTS, BARCELONA

A series of lightweight 250kg, 500kg and 1,000kg manual overhead cranes for sensitive equipment handling and maintenance.

Due to the nature of the clients facility and the overhead crane systems being set within the roofs of the chambers, it was not possible to have parallel running tracks and there was also a requirement to accommodate curves within the track to align to the chamber roof as closely as possible.

Our design team needed to consider a lifting solution with these considerations in mind whilst also addressing the reduced headroom working capacity.

READ MORE
Alba Synchrotron Radiation Facility Particle Accelerator 1